INDIANAPOLIS — The Madison Avenue and Mooresville Road Bypass bridges over I-465 on the south side of Indianapolis are expected to close next month. The bridges are expected to close for replacement in mid- to late February.
The Madison Avenue bridge is expected to be closed for just over six months. The Mooresville Road Bypass bridge is scheduled to close for about three months. For schedule updates, visit I69FinishLine.com to sign up for project updates or follow I-69 Finish Line on Facebook, Twitter and Instagram.
Both bridges will be demolished and fully reconstructed during the closures. The Madison Avenue detour will follow Thompson Road, Keystone Avenue and Hanna Avenue. The Mooresville Road Bypass detour will follow Mann Road, Thompson Road and High School Road. Signage is being posted to alert drivers of the extended closures.
When work begins, I-465 traffic should expect nighttime lane closures and 20-minute traffic stoppages between 11 p.m. and 5 a.m. No demolition work will happen over live traffic.
-
Other News This Week
- This Week’s Issue: June 28-July 3
- 100 Years Ago: June 28-July 2
- Door To Door
- Eclipse Had Major Economic Impact in Indiana
- Exploring Monument Circle Talk at Central Library July 2
- Butler College Romances
- Graceland Gentrification? Part 2
- Applause!: June 28-July 3
- 3rd Annual Irvington Pride June 29
- Near Eastside Building Set for Redevelopment
Search Site for Articles