INDOT Notes 1 Year Progress on North Split

INDIANAPOLIS — The Indiana Department of Transportation is providing a progress update on the North Split reconstruction project one year after the interchange’s full closure.
Since May 15, 2021, North Split construction crews have:
• Successfully demolished 38 of 51 bridges in need of repair
• Placed 217 of 390 precast concrete beams, with the largest weighing approximately 250,000 pounds
• Reconstructed 4 bridges and 1 ramp, which are currently in use
• Used approximately 34,000 cubic yards of structural concrete
• Moved over 560,000 cubic yards of the 1 million total cubic yards of earthwork
The North Split is the busiest interchange in central Indiana. After 50 years of service, the North Split’s deteriorating condition made reconstruction necessary to rehabilitate and improve the existing interstate facilities.  A more efficient and compact redesign of the interchange eliminates merging and weaving conditions that contribute to high crash rates and congestion.
The interchange is scheduled to reopen by the end of 2022 with landscaping, aesthetics and local street work continuing into spring 2023. The North Split landscaping design will include the use of native, low-maintenance plants to soften urban elements and provide a diverse palette of plant species, including native grasses, small shrubs, large deciduous shrubs, ornamental trees, and shade trees.
The project will also result in improved lighting, visibility and pedestrian safety at bridge underpasses.
For up-to-date project information, visit northsplit.com or text “NORTHSPLIT” to 468311.