INDIANAPOLIS – The Indiana Department of Transportation will close a portion of I-70 Eastbound and Westbound for approximately 30 days each.
I-70 EB from Ronald Reagan Parkway to the South Split will close on May 22. All lanes are scheduled to reopen on June 28.
I-70 WB from the South Split to Ronald Reagan Parkway will close on June 26. All lanes are scheduled to reopen on July 30.
These closures will remain in effect during the Memorial Day and July 4th holiday weekends.
Crews will be concrete patching and working on bridge joints and bridge decks during the full closures.
All collector lanes will be open to and from the Indianapolis International Airport during the full closures.
During the closures, drivers are encouraged to find alternate routes and plan extra time to travel.
• From the airport to I-70 EB: Take the collector lanes to I-465 NB around to I-70 EB.
• I-70 WB to the airport: Take I-465 SB around to Ronald Reagan collector lanes to get to the airport. Or continue North on I-465 to get back to I-70 WB.
INDOT and contractor partner, Rieth-Riley, are accelerating planned construction on I-70 to allow work to be done before major events rescheduled due to the COVID-19 public health emergency resume. Full interstate closures are being used to ensure safety for workers, reduce the overall construction time, and maximize use of taxpayer dollars.
In construction zones, please slow down and pay attention. During the full closures, be prepared to find alternate routes.
-
Other News This Week
- IndyPL Recognized by Employ Indy
- 100 Years Ago: April 11-17
- Applause!: April 11-17
- Día del Niño at Be My Neighbor Day
- Farming Organizations Awarded Funding for Food Chain Resiliency
- Encore Showing of “Champions of the Golden Valley”
- MLK Gateway Project Begins
- The Poetry of April: Redux
- School Staff Team up to Help Zoey’s Place
- This Week’s Issue: April 11-17
Search Site for Articles