INDIANAPOLIS — Milestone Contractors plans to begin work on or after April 4 on a $4.2 million pavement repair and resurface project on I-74 between I-465 and London Road (Exit 103). Construction zone signs will be placed in late March.
Concrete pavement repairs will require weekend lane closures starting at 9 p.m. on Fridays until 6 a.m. on Mondays for approximately one month. Specific dates and locations of closures will be announced in advance.
Weather permitting, asphalt patching and paving is scheduled to begin in early May and will require overnight lane closures between 9 p.m. and 6 a.m. through the summer. Afterward, new lane markings, reflective pavement markers and shoulder corrugations will be installed.
The nine-mile project on I-74 southeast of Indianapolis is expected to be complete before October.
Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.
-
Other News This Week
- The Ghost of I.U.’s Lambda Chi Alpha
- “Little Shop of Horrors” at the IRT
- Eastside Agrapreneur Passes Away
- Birds On The Lawn
- Free Mammograms Available at Certain Francisan Health Locations
- The Answers are in the Almanac
- Eclipse Reflections
- “Acts of Faith” Exhibit at the Eiteljorg Opens April 20
- Working Cats Need Adopters
- 100 Years Ago: April 19-25
Search Site for Articles