INDIANAPOLIS — Milestone Contractors plans to begin work on or after April 4 on a $4.2 million pavement repair and resurface project on I-74 between I-465 and London Road (Exit 103). Construction zone signs will be placed in late March.
Concrete pavement repairs will require weekend lane closures starting at 9 p.m. on Fridays until 6 a.m. on Mondays for approximately one month. Specific dates and locations of closures will be announced in advance.
Weather permitting, asphalt patching and paving is scheduled to begin in early May and will require overnight lane closures between 9 p.m. and 6 a.m. through the summer. Afterward, new lane markings, reflective pavement markers and shoulder corrugations will be installed.
The nine-mile project on I-74 southeast of Indianapolis is expected to be complete before October.
Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.
-
Other News This Week
- 68th Indiana Flower + Patio Show Opens March 14
- Colorectal Cancer, a Highly Curable Disease If Caught Early
- This Week’s Issue: March 6-12
- Celebrate Women’s History Month with Special Event
- New Law Would Make Sleeping in Public Spaces Illegal
- Phase II of Level Up 31 Begins
- Pulitzer Prize–winning “English” comes to the IRT
- The Lyric Theatre & Sinatra
- Indy Parks Announces New Deputy Director
- Doing
Search Site for Articles