INDIANAPOLIS — Milestone Contractors plans to begin work on or after April 4 on a $4.2 million pavement repair and resurface project on I-74 between I-465 and London Road (Exit 103). Construction zone signs will be placed in late March.
Concrete pavement repairs will require weekend lane closures starting at 9 p.m. on Fridays until 6 a.m. on Mondays for approximately one month. Specific dates and locations of closures will be announced in advance.
Weather permitting, asphalt patching and paving is scheduled to begin in early May and will require overnight lane closures between 9 p.m. and 6 a.m. through the summer. Afterward, new lane markings, reflective pavement markers and shoulder corrugations will be installed.
The nine-mile project on I-74 southeast of Indianapolis is expected to be complete before October.
Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.
-
Other News This Week
- 100 Years Ago: June 19-25
- Arts for Learning Indiana Community Open House June 27
- Irvington Pride 2026 Tab
- Eastside Games Highlight Great Neighborhood June 20-27
- Eskenazi Mental Health Center Expands Services
- Applause!: June 19-25
- Irvington Historical Society Receives Grant
- State Awards Grants to Help Victims of Crime
- Eastside Data Center Proposal Clears Hurdle
- This Week’s Issue: June 19-25
Search Site for Articles