INDIANAPOLIS — Milestone Contractors plans to begin work on or after April 4 on a $4.2 million pavement repair and resurface project on I-74 between I-465 and London Road (Exit 103). Construction zone signs will be placed in late March.
Concrete pavement repairs will require weekend lane closures starting at 9 p.m. on Fridays until 6 a.m. on Mondays for approximately one month. Specific dates and locations of closures will be announced in advance.
Weather permitting, asphalt patching and paving is scheduled to begin in early May and will require overnight lane closures between 9 p.m. and 6 a.m. through the summer. Afterward, new lane markings, reflective pavement markers and shoulder corrugations will be installed.
The nine-mile project on I-74 southeast of Indianapolis is expected to be complete before October.
Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.
-
Other News This Week
- New HIP Work Requirements Introduced
- Midwest Seeing Surge in Tick Bites
- District Theatre Presents “They Call Me Genêt”
- This Week’s Issue: July 10-16
- Library Introduces New Bookmobiles
- Special Zoning District for Data Centers Put Forward
- From Hell Gate to the Golden Gate in a Maxwell 30
- 100 Years Ago: July 10-16
- New Train Ride at Indiana State Fair
- Benton House Book Sale July 17-19
Search Site for Articles