INDIANAPOLIS — Milestone Contractors plans to begin work on or after April 4 on a $4.2 million pavement repair and resurface project on I-74 between I-465 and London Road (Exit 103). Construction zone signs will be placed in late March.
Concrete pavement repairs will require weekend lane closures starting at 9 p.m. on Fridays until 6 a.m. on Mondays for approximately one month. Specific dates and locations of closures will be announced in advance.
Weather permitting, asphalt patching and paving is scheduled to begin in early May and will require overnight lane closures between 9 p.m. and 6 a.m. through the summer. Afterward, new lane markings, reflective pavement markers and shoulder corrugations will be installed.
The nine-mile project on I-74 southeast of Indianapolis is expected to be complete before October.
Motorists can learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.
-
Other News This Week
- The Bona Thompson Memorial Center
- Applause!: Nov. 22-28
- Judge Not
- Safe Park Indy Requests Donations
- Library Employees Receive Scholarships
- Merry Movie Nights at Heartland
- Grill Plates
- New Indoor Theater to be Built in Murphy Arts Center
- Caring Recovery Opioid Treatment Program Opens on Eastside
- Hancock Co. Breaks Ground on Amplify Hancock
Search Site for Articles